Skip to main content

No Burn Advisory

Mesa County Public Health has issued a No Burn Advisory from Saturday, June 6 at 7 a.m. until Monday, June 15 at 9 p.m. due to fire danger. Burning of any kind, including agricultural burning, is not allowed during this advisory period. Check conditions on our Air Quality webpage.

Mesa County is continuing work to improve the E Road corridor in Clifton, with the E Road Phase 3 project moving closer to construction along E Road between the Green Acres subdivision and 33 Road.

On May 19, the Board of Mesa County Commissioners approved a $275,390 change order with HDR Engineering, Inc. for additional engineering, environmental and construction support services needed to move the project forward.

The E Road corridor is a key east-west connection in the Clifton area, serving neighborhoods, schools, businesses and daily commuters. Planned improvements are intended to improve traffic flow, safety and long-term transportation reliability as the area continues to grow.

Additional work approved through the change order includes utility coordination, right-of-way support, environmental clearances and construction-phase engineering services. The project is expected to move into construction in 2027.

Mesa County previously completed the E Road Phase 2B project, which included roadway and multimodal improvements west of the current Phase 3 corridor.

Public Works
News
Blog Post, Information, Video
An aerial view of a newly improved roadway and roundabout intersection in a residential area, with homes, trees and mesas visible in the background.